Facts & Features

Building Details

  • Located in the 700 block of S. 8th Street across from the 730 S. 8th hospital entrance
  • Six floors of clinics and services, plus two levels of underground parking for patients and their families and a seventh floor utility penthouse
  • 377,000 square feet
  • Primary care, specialty care, physical therapy/occupational therapy
  • Same day surgery center with 5 operating rooms (2 shelled) and 4 GI/endoscopy rooms
  • Cancer Center with Radiation Therapy
  • Outpatient Imaging Center, Women’s Imaging
  • Financed with Hennepin County issued bonds, service on bonds paid by Hennepin Healthcare Systems, Inc. operating revenues

Connective Features

  • 2nd level Skyway connection to the Red Building
  • Tunnel to Orange Building
  • MTC bus stops
  • LRT stations 3 blocks north
  • Bike parking
  • 220 parking stalls underground for patient parking

Project Timeline / Milestones

  • Schematic design completed June 2015
  • Groundbreaking and start of construction November 2015
  • New building opens in January 2018

Construction and Design Partners

Architect: BWBR

Contractor: Mortenson Construction